Company news, Featured, From the magazine, News

View the latest trenchless technology tenders

trenchless tenders

Belaringar Creek Syphon Pipe Replacement

Issued by: Public Works Advisory

Closing Date: 19/05/2022

Location: New South Wales

Description: The Albert Priest Channel which supplies raw water from Warren to Nyngan consists of a DN900 reinforced concrete (RC) pipeline across the Belaringar Creek. This existing pipeline (hereinafter called “syphon”) has deteriorated and needs replacement. The designed capacity of the syphon is 60 ML/d.

Under this contract, a new syphon pipeline across and under the Belaringar creek shall be constructed together with associated structures such as headwalls as stated in this tender document. The new syphon shall be installed parallel to the existing syphon and connected to the existing open channel section on both ends

Provision of stormwater pipe relining & associated works

Issued by: Hume City Council

Closing Date: 12/05/2022

Location: Victoria

Description: Provision of stormwater pipe relining & associated works

Harrier Parade Sewer Pump Station 3C Upgrade

Issued by: Tamworth Regional Council

Closing Date: 12/05/2022

Location: New South Wales

Description: Council is seeking a suitably qualified contractor for the construction of the upgrade of Harrier Parade Sewer Pump Station (SPS). Due to increased network flows and the need for additional emergency storage, the Harrier Parade Sewer Pump Station 3C is to be upgraded to pump an ultimate loading of 70.8 L/s with two pumps in a duty/standby arrangement. This will be via a new SPS constructed adjacent to the existing SPS.

Umbakumba – Bore Rising Main and Associated Infrastructure Diversion and Sewer Pump Station Upgrade and New Sewer Rising Main

Issued by: Power and Water Corporation

Closing Date: 25/05/2022

Location: Northern Territory

Description: Umbakumba is a remote aboriginal community located east of Angurugu near Little Lagoon and Port Langdon on the north east coast of Groote Eylandt. Umbakumba has a population of 549 people. A new subdivision is planned to the south west of the community. The location of the new subdivision has resulted in the diversion of the bore rising main and associated infrastructure.

The bore rising main and associated infrastructure diversion is a priority and must not be delayed due to any sewer SPS and sewer rising main works.

The existing sewage pump station (SPS) #1 was built in 1981. It was identified in the Strategic Indigenous Housing and Infrastructure program (SIHIP) that the SPS and rising main was undersized resulting in the SPS upgrade and new sewer rising main works.

Spark – North East Link Project – CCTV (Stormwater Drains and Sewer)

Issued by: Capella Capital Pty Limited

Closing Date: 26/05/2022

Location: Victoria

Description: Express interest for the CCTV (Stormwater drains & Sewer) opportunity.

Water Mains Upgrade (Stage 3)

Issued by: Cook Shire Council

Closing Date: 18/05/2022

Location: Queensland

Description: Cook Shire Council invites tenders from suitably qualified tenderers for construction of the Cooktown Water Mains replacement and all supporting infrastructure as described in more detail in the document.

Email support@australiantenders.com.au for more information.  

For more tender information visit the Australian Tenders website