Bothar Boring has delivered a complex package of trenchless works for the Bonds Creek expansion project in Sydney.

Following the successful completion of 872m of tunnelling for the Kemps Creek dual pressure water mains project, Bothar is proud to announce the completion of yet another significant package of works, delivering over 500 metres of trenchless installation for the Bonds Creek Carrier Extension Project, in collaboration with it’s valued partner, Quickway.

This project saw Bothar use a comprehensive range of trenchless construction techniques and equipment, including auger boring, a laser-guided vacuum system, and an AVN600 microtunnelling machine.

This diverse methodology allowed Bothar to effectively navigate varying and challenging ground conditions across the project. The strategic selection and application of each method played a critical role in ensuring the seamless and timely delivery of the project within tight schedule constraints.

Bothar’s dedication to safety, precision and efficiency under pressure again demonstrated its ability to deliver complex trenchless infrastructure with consistency and reliability.

“We are proud of our workforce, our technical team and our project partners who contributed to this success,” Bothar told Trenchless Australasia.

The company extended gratitude to Quickway for its continued trust in Bothar’s capabilities.

“Quickway’s support has been instrumental in the successful execution of this project, and we look forward to building on this strong partnership in future ventures,” Bothar said.

Bothar is no stranger to multifaceted projects such that require the use of various methodologies. The company leverages decades of experience, a robust safety culture and an extensive fleet of specialised equipment to deliver complex trenchless solutions in a turnkey package.

Bothar is committed to high-quality, safe infrastructure development and continues to grow rapidly, expanding across additional regions and projects. With each endeavour, Bothar sets new benchmarks for itself in safety, innovation and community impact minimisation, solidifying its position as a leader in the trenchless technology sector.

Following the successful completion of 872m of tunnelling for the Kemps Creek dual pressure water mains project, Bothar is proud to announce the completion of yet another significant package of works, delivering over 500 metres of trenchless installation for the Bonds Creek Carrier Extension Project, in collaboration with it’s valued partner, Quickway.

This project saw Bothar use a comprehensive range of trenchless construction techniques and equipment, including auger boring, a laser-guided vacuum system, and an AVN600 microtunnelling machine.

This diverse methodology allowed Bothar to effectively navigate varying and challenging ground conditions across the project. The strategic selection and application of each method played a critical role in ensuring the seamless and timely delivery of the project within tight schedule constraints.

Bothar’s dedication to safety, precision and efficiency under pressure again demonstrated its ability to deliver complex trenchless infrastructure with consistency and reliability.

“We are proud of our workforce, our technical team and our project partners who contributed to this success,” Bothar told Trenchless Australasia.

The company extended gratitude to Quickway for its continued trust in Bothar’s capabilities.

“Quickway’s support has been instrumental in the successful execution of this project, and we look forward to building on this strong partnership in future ventures,” Bothar said.

Bothar is no stranger to multifaceted projects such that require the use of various methodologies. The company leverages decades of experience, a robust safety culture and an extensive fleet of specialised equipment to deliver complex trenchless solutions in a turnkey package.

Bothar is committed to high-quality, safe infrastructure development and continues to grow rapidly, expanding across additional regions and projects. With each endeavour, Bothar sets new benchmarks for itself in safety, innovation and community impact minimisation, solidifying its position as a leader in the trenchless technology sector.

See it all at No-Dig Down Under

Bothar Boring is a bronze sponsor of this year’s No-Dig Down Under, the Southern Hemisphere’s only large-scale conference and exhibition dedicated to trenchless technology.

Organised in partnership with the Australasian Society for Trenchless Technology, the event returns to the Melbourne Convention and Exhibition Centre from 17–18 September.

No-Dig Down Under 2025 will also be co-located with Converge, a new premier event in the municipal works, civil and commercial construction space.

The Bothar team will be on the ground at No-Dig Down Under, showcasing its capabilities in the trenchless space, teeing up collaborations, and networking with industry colleagues.

For more information, visit botharboring.comBothar Boring is a bronze sponsor of this year’s No-Dig Down Under, the Southern Hemisphere’s only large-scale conference and exhibition dedicated to trenchless technology.

Organised in partnership with the Australasian Society for Trenchless Technology, the event returns to the Melbourne Convention and Exhibition Centre from 17–18 September.

No-Dig Down Under 2025 will also be co-located with Converge, a new premier event in the municipal works, civil and commercial construction space.

The Bothar team will be on the ground at No-Dig Down Under, showcasing its capabilities in the trenchless space, teeing up collaborations, and networking with industry colleagues.

For more information, visit botharboring.com

This article was featured in the June edition of Trenchless Australasia.

Subscribe to Trenchless Australasia for the latest project and industry news

Send this to a friend